Math Problem Statement

Activity Times and Predecessors Activity Description Predecessors (a) (m) (b) A Drain Oil --- 3 5 10 B Replace Filter A 2 4 9 C Refill Oil B, E 3 5 8 D Check Tyres --- 1 5 9 E Wash Windows D 2 5 8 F Fill Fluids E 2 5 10 G Final Test C, F 2 6 9 NB: Time periods are in weeks Draw the activity network for this problem (either AON or AOA). Determine the expected time and variance for each activty. Show the activity schedule (ES,EF, LS, LF) as well as the slack. Show the results in a table. Determine and state the critical path for this project. this must be based on your work at C, not by inspection. What is the expected time, variance and standard deviation of this project? What is the probability that the project will be finished within 59 days?

Solution

Ask a new question for Free

By Image

Drop file here or Click Here to upload

Math Problem Analysis

Mathematical Concepts

Project Management
Critical Path Method
Expected Time Calculation
Variance Calculation
Standard Deviation

Formulas

Expected Time (TE) = (a + 4m + b) / 6
Variance = ((b - a) / 6)^2
Standard Deviation = sqrt(Variance)

Theorems

-

Suitable Grade Level

Advanced