Math Problem Statement
Activity Times and Predecessors Activity Description Predecessors (a) (m) (b) A Drain Oil --- 3 5 10 B Replace Filter A 2 4 9 C Refill Oil B, E 3 5 8 D Check Tyres --- 1 5 9 E Wash Windows D 2 5 8 F Fill Fluids E 2 5 10 G Final Test C, F 2 6 9 NB: Time periods are in weeks Draw the activity network for this problem (either AON or AOA). Determine the expected time and variance for each activty. Show the activity schedule (ES,EF, LS, LF) as well as the slack. Show the results in a table. Determine and state the critical path for this project. this must be based on your work at C, not by inspection. What is the expected time, variance and standard deviation of this project? What is the probability that the project will be finished within 59 days?
Solution
Ask a new question for Free
By Image
Drop file here or Click Here to upload
Math Problem Analysis
Mathematical Concepts
Project Management
Critical Path Method
Expected Time Calculation
Variance Calculation
Standard Deviation
Formulas
Expected Time (TE) = (a + 4m + b) / 6
Variance = ((b - a) / 6)^2
Standard Deviation = sqrt(Variance)
Theorems
-
Suitable Grade Level
Advanced
Related Recommendation
Solving Project Management Problems: Critical Path and Crashing Costs Explained
Project Management at Hard Rock Café: PERT and CPM Analysis for Rockfest Planning
Solve Project Management Activities Cost Optimization Problem
Investment Analysis: Expected Return and Risk Calculation for Stocks, Bonds, and Portfolio
Critical Path Delay and Cost Optimization in Project Scheduling